By providing your contact information to Jack McCann with, your personal information will be processed in accordance with Jack McCann with's Privacy Policy. By checking the box(es) below, you consent to receive communications regarding your real estate inquiries and related marketing and promotional updates in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. You may opt out of receiving further communications from Jack McCann with at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe.
Thank you for your message. We will be in touch with you shortly.
Explore Our Properties
Jack McCann Multifamily in Seaside Lagoon

Seaside Lagoon Rebuild: What Redondo Beach Owners Should Know

Jack McCann  |  November 1, 2026

Around Town · The Pier

Redondo Beach’s Seaside Lagoon rebuild moves forward

Redondo Beach chose to send its long-delayed lagoon rehab to the Coastal Commission now, rather than pause for a wave-pool idea. Here’s what was decided, who argued which side, and what it means if you own near the harbor.

Redondo Beach’s Seaside Lagoon rebuild cleared a key hurdle on September 15, when the City Council voted unanimously to finish and submit a Coastal Development Permit application for the project at 200 Portofino Way and approved its environmental exemption. For anyone following Redondo Beach real estate, especially owners of apartment buildings near King Harbor, it’s a waterfront decision worth understanding. The alternative on the table was to hold off and study other ideas, including a large surf park pitched by BeachLife Festival founder Allen Sanford.

Mayor Jim Light called it the closest the city has come to construction after roughly two decades of debate. It is not a final approval. Seaside Lagoon sits in tidelands where the California Coastal Commission keeps permitting authority, so nothing gets built until the Commission signs off.

State grant

$10M

City contribution

$1M

Phase 1 estimate

$9.47M

As of April 2026

2026 admissions

67,000+

Over 104 open days

Latest 2-year fines

$175K

After negotiation

Coastal review

4–6 mo

Staff estimate

What does the Seaside Lagoon rebuild include?

Today the lagoon pulls seawater in from the harbor, treats it for swimming, then treats it again before sending it back out. That aging flow-through system is the source of the city’s recurring water-quality fines, and a pump failure in 2025 closed the lagoon for about two weeks and cost roughly $60,000 to fix.

Phase 1 replaces it with a closed, filtered lagoon of about 770,000 gallons that recirculates continuously. Plans call for roughly an acre of swimming area up to five feet deep, a sandy zero-depth entry that slopes into a concrete-bottom section, a water slide, splash features, an ADA ramp, and a new restroom and shower building. New fencing is designed so more of the park can stay open when the swim area is closed.

Who supported the rebuild, and who wanted to wait?

Move forward now

City staff, the council, many public speakers

Supporters said every season of delay means more fines and repair bills on a system that’s past its life. Staff put fines and related environmental-project costs at more than $900,000 combined. Moving now also protects the $10 million in state money and opens more of the park year-round. Mayor Light stressed this is only Phase 1, with later phases to be considered as funding allows.

Pause and reconsider

Harbor Commission, wave-pool backers, other residents

In August the Harbor Commission unanimously advised against the design as presented. It asked the city to explore a deeper lagoon that keeps saltwater and a sand bottom, adds more year-round amenities, plans for sea-level rise, and seeks more time on the state funding. Wave-pool supporters argued a surf park alongside a smaller family lagoon would draw more visitors and add revenue to the city.

How did the Seaside Lagoon plan get here?

When

What happened

Status

2021

State appropriates $10 million for the lagoon’s rehabilitation

Funded

Apr 2026

Council unanimously backs a scaled-back Phase 1 after a lagoon-plus-lap-pool design topped $16 million

Adopted

Aug 25

Harbor Commission recommends against the design as presented

Advisory

Sep 14

Harbor Commission receives the wave-pool concept as an information item

No vote

Sep 15

Council votes unanimously to submit the Coastal Development Permit application

Approved

Next

Coastal Commission review, then construction plans, bidding and construction

Pending

What multifamily owners need to know
  1. 01

    This is a permit filing, not a groundbreaking

    Staff expect four to six months of Coastal Commission review, and the Commission can require design changes. Treat any construction timeline as tentative until the permit is issued.

  2. 02

    Plan for construction near Portofino Way

    Once work starts, expect activity around the pier and marina. If you own apartments close to the harbor, give tenants a heads-up early and watch for city notices about access and parking.

  3. 03

    A year-round park is a real amenity

    The new fencing plan keeps more of the grounds open outside swim season. For buildings within walking distance, a modernized waterfront park is a fair point to mention in rental listings once it’s open.

  4. 04

    Keep an eye on the wave-pool talks

    The city says it isn’t negotiating a wave pool, but it has held separate closed-session real estate talks with Sanford and BeachLife over parts of the marina lot and lagoon. A bigger regional draw would bring more visitors, and more traffic, to the harbor.

  5. 05

    Underwrite what’s built, not what’s planned

    Buyers and lenders price today’s rents and today’s rates. Waterfront upgrades can help over time, but your property’s numbers should stand on their own before any of this opens.

At Jack McCann Multifamily Advisors, we’re telling owners of apartment buildings near the harbor to treat the lagoon as a long-range plus, not a reason to change the plans they have in place as of October 2026. If you want to see where your building stands today, our free Stress Test runs the numbers in a few minutes.

What does the lagoon rebuild mean for sellers and buyers?

Sellers

Don’t wait on the lagoon to list

With Coastal Commission review still ahead and no construction date, buyers won’t pay today for a park that isn’t built. Price on current rents and condition.

Use it as a talking point

A $10 million state-funded rebuild near the pier is a fair line in the marketing for a building within walking distance. Our blog on South Bay apartment sales and pricing can help you back up your asking price.

Buyers

Underwrite the property as it stands

Value an investment property near the harbor on its in-place numbers, and treat a finished lagoon as possible upside rather than a given.

Budget for disruption

Expect construction around Portofino Way once permitted, and more harbor traffic if a larger attraction like a wave pool comes back. For more on how we evaluate South Bay deals, see our latest multifamily market posts.

Redondo Beach Real Estate FAQ: Seaside Lagoon Rebuild

When will construction on the Seaside Lagoon rebuild start?

There’s no construction date yet. The City Council voted on September 15, 2026 to submit a Coastal Development Permit application, and city staff expect Coastal Commission review to take four to six months. Construction plans, bidding and construction follow only after the permit is issued.

How is the Seaside Lagoon rebuild being paid for?

The State of California appropriated $10 million for the lagoon’s rehabilitation in 2021, and the city is contributing about $1 million. As of April 2026, Phase 1 was estimated at roughly $9.47 million.

Is a wave pool part of the Seaside Lagoon plan?

No. The council chose to move ahead with the lagoon rehab rather than pause for a surf park proposed by BeachLife Festival founder Allen Sanford. The city says it isn’t negotiating a wave pool, though it has held separate closed-session real estate talks with Sanford over parts of the marina lot and lagoon.

Will the rebuild change the Redondo Beach real estate market for apartment buildings?

Not yet. Nothing has been built, the Coastal Commission still has to approve the permit, and buyers and lenders price today’s rents and rates. Once it opens, a modernized year-round park could become a selling point for apartment buildings within walking distance of the harbor.

How should buyers value an investment property near Seaside Lagoon?

Underwrite the property on its current income and expenses, and treat a finished lagoon as possible future upside. Buyers should also expect construction activity near Portofino Way once work is permitted.

Jack McCann Multifamily Stress Test

How would your property hold up today?

Our free Stress Test runs your building’s income, expenses and debt against current rates and recent South Bay sales, so you know where you stand before you make your next move. Only 10 FREE slots per month, get yours before it’s booked out.

Start your free Stress Test >

Sources: Patch (Sept. 16, 2026), Citizen Portal summary of the Sept. 15 City Council meeting, The Inertia (Sept. 17, 2026), and City of Redondo Beach meeting records.